Silvercorp Metals Revises El Domo Project Budget Upward to $284 Million

Silvercorp Metals increased its El Domo Project construction budget by $44 million to $284 million, citing higher VAT rates in Ecuador, expanded process plant scope, and added infrastructure costs, but expects VAT recovery as a tax credit in the first year of operations.

Philly Metrowire Staff
••Business
Silvercorp Metals Revises El Domo Project Budget Upward to $284 Million

Silvercorp Metals Inc. (TSX: SVM) (NYSE American: SVM) has updated the construction budget and schedule for its El Domo Project, now estimating total capital costs at $284 million, a $44 million increase from the $240 million estimate released on March 31, 2025. The revision reflects higher value-added tax (VAT) rates in Ecuador, an expanded and refined process plant scope, additional infrastructure and owner-related costs, and previously omitted engineering, supervision, and environmental items. These increases were partially offset by lower mining and stripping costs, project-level savings, and a reduced contingency allowance.

The company stated that the higher VAT is expected to be recovered as a tax credit in the first year of operations once concentrate exports begin. The reduced contingency reflects more detailed engineering and improved cost certainty as construction progresses. The full press release is available at https://ibn.fm/mP1DG.

Silvercorp is a Canadian mining company that produces silver, gold, lead, and zinc, with a history of profitability and growth potential. The company's strategy focuses on generating free cash flow from long-life mines, organic growth through extensive drilling, ongoing merger and acquisition efforts, and a commitment to responsible mining and ESG. For more information, visit https://ibn.fm/SVM.

The El Domo Project budget update is significant as it reflects the company's progress and increased cost certainty in advancing the project. The higher VAT rates in Ecuador, while adding to upfront costs, are recoverable and thus do not represent a permanent expense. The reduction in contingency indicates that engineering and planning have reached a stage where uncertainties are better understood, reducing the risk of further cost overruns. This announcement provides investors with a clearer picture of the project's financial requirements and timeline, which is critical for assessing the company's near-term capital allocation and potential return on investment.

Silvercorp's ability to manage project costs and navigate local tax regimes is essential for maintaining its profitability and growth trajectory. The revised budget underscores the challenges of developing mining projects in jurisdictions with evolving fiscal policies, but also demonstrates the company's proactive approach to addressing these issues. As the project moves forward, stakeholders will monitor whether the revised estimates hold and if the VAT recovery materializes as planned, which could impact the company's cash flow and financial health.